Question
The Perform Quality Assurance process on a project could create the requirement to update which of the following documents?
A.) Quality Management Plan
B.) Project Charter
C.) Scope Statement
D.) Enterprise Environmental Factors
Question provided by The PM Exam Simulator: www.pm-exam-simulator.com
Answer & Explanation
Correct Answer: A)
After the Quality Audit, you may have to create some change requests. The Quality Management Plan might get changed if the change requests are approved. You cannot change the Project Charter, Enterprise Environmental Factors, or Scope Statement.
Reference: PMBOK Guide 5th Edition, page 248