Project ManagementWaterfall

Free PMP® Exam Sample Question

Question

You are conducting an electrical network and fixtures installation project. During project execution, your quality auditors highlighted some defects in the work performed. You analyze the situation and determine that these are genuine defects that need to be fixed. You submit a change request, which is approved and the team performs the necessary defect repairs. Which of the following is incorrect regarding this scenario?

A.) You have followed the change control system

B.) You have performed the Monitor and Control Project Work process

C.) You have performed the Integrated Change Control process

D.)You should document these defect repairs in the Project Management Plan

Question provided by The PM Exam Simulator: www.pm-exam-simulator.com

Answer & Explanation

Correct Answer: D)

We are looking for the statement that is NOT true:

> Because you were able to identify the defects, you have performed the Monitor and Control Project Work process.

> Similarly, as you were able to remove the defects, you have performed the Integrated Change Control process as well.

> As you have performed both processes, you have followed the change control system.

All of these choices are true about the situation.

The only statement that is not true is the fact that details of defect repairs are not documented in the Project Management Plan (this detail is documented in the Change Request Log.)

Reference: PMBOK Guide 5th Edition, page 100

Disclaimer and Copyright Statement

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Related posts

PMP v3 Ending June 30th

Abhinav Kaiser

Is a Scrum Master the Agile Version of a Project Manager?

Abhinav Kaiser

Objects in the Rear-View Mirror Appear Closer Than They Are

Abhinav Kaiser

PMP Exam Tip: Prepare Mentally for the Day of the PMP Exam

Abhinav Kaiser

Agile is Common Sense

Abhinav Kaiser

The PMP Exam Changes in 2013. Here’s What You Need to Know.

Abhinav Kaiser

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.