Project ManagementWaterfall

PMP Exam Sample Question

Question

A content writing firm established a productivity figure of 10 pages/hour. This figure was identified by a benchmarking firm specializing in the test engineering industry.

Every quarter the company’s senior management conducts a management review of the productivity figures. The latest productivity figures show that projects using word processing software installed on the users’ PC were able to beat the target with a productivity of 15 pages/hour, while web-based content writing projects are at 5 pages/hour.

Senior management is not satisfied with the performance of the web-based projects and requests an investigation with the help of the quality department. The goal is to understand why web-based content is missing the mark. After a detailed analysis the quality assurance department issues a report illustrating the reason why some projects are exceeding the goal while others are not.

Based on your understanding of benchmarking what are possible reasons for the above scenario?

A.) The benchmarking figures utilized were derived from a different industry

B.) The original benchmarking was done only for projects using locally-installed software and did not include web-based development

C.) Project managers lack monitoring tools for project metrics in order to meet organizational goals

D.) Benchmarking never works in a creative production environment

Question provided by The PM Exam Simulator: www.pm-exam-simulator.com

Answer & Explanation

Correct Answer: A)

Benchmarking is an activity performed within the organization or across organizations to compare data from similar projects/parameters. The content writing firm should have taken data for the type of projects that it executes rather than picking up industry benchmarks on productivity for a testing firm. Therefore “The benchmarking figures utilized were derived from a different industry” is the best explanation of what is going on here.

The second best option to select would have been that “The original benchmarking was done only for projects using locally-installed software and did not include web-based development”. However, there are two problems with this answer: The scenario does not give us any indication that the original benchmarking had indeed been performed like this and the fact that “The benchmarking figures utilized were derived from a different industry” is a more generic and therefore the better answer here.

The answer “Project managers lack monitoring tools for project metrics in order to meet organizational goals” can obviously not be correct because the scenario discusses that we know exactly what the actual results are, therefore the monitoring is in place.

Last but not least, “Benchmarking never works in a creative production environment” is not a good answer, because it contains the word never. Always be wary of absolutes in answers. Answers with “always”, “never” and other absolutes are usually incorrect, because project management is never black and white.

Reference: PMBOK Guide Fifth Edition, page 239

Disclaimer and Copyright Statement

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Related posts

PMPĀ® Exam Lessons Learned From Someone Who Has Recently Passed

Abhinav Kaiser

PMP v3 Ending June 30th

Abhinav Kaiser

Top 10 Features of a Great PMP Exam Simulator

Abhinav Kaiser

Project Management starts with People Management

Abhinav Kaiser

Understanding The PDU Category Structure And Policies

Abhinav Kaiser

Growth through Innovationā€¦

Abhinav Kaiser

Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.